October 4, 2022
The masonry work on the west wall facing Orleans (Native child mural) is done. Rough openings are complete, and all the brick is stable and plumb. As a bonus, the central figure in the mural is in relatively good shape.
October 4, 2022
The masonry work on the west wall facing Orleans (Native child mural) is done. Rough openings are complete, and all the brick is stable and plumb. As a bonus, the central figure in the mural is in relatively good shape.
July 18, 2022
We received our permit from the building department to start exterior work. DTE is making a plan to protect the utility lines to and around the building. A flow test has confirmed we have sufficient water available for fire suppression.… Continue Reading…
June 18, 2022
Skip saw an ad pop up on line on Thursday evening past. “Bar & equipment for 2K,” it said. “Uhhh, fridges, too? Glasswasher? Sinks? Server station?” I asked. “Each of those fridges is worth 2K used!” He contacted the seller,… Continue Reading…
October 5, 2021
… It just doesn’t look like it, yet. We’ve received our Federal licenses, and had our interview with the MLCC, which are milestones. Still working on the final construction plans. And pacing. A lot of pacing. Also gadget work, on… Continue Reading…